Our amazing new ourdoor swimming pool is slated to be completed for July 1, 2025. The construction is quickly coming along and we all can't wait for it to be fully completed.
Construction of the 4,000 square foot change house by Home Hardware continues into the winter. Home In addition to the centrally located office, they will be constructing 3 change rooms – male, female and family/accessible rooms. The mechanical room will host the newest in pool equipment as well as supplying utilities to the office and change rooms. The building will be entirely enclosed and heated.
Western Recreation – the pool basin contractor – completed the first phase of the pool tank construction in September. The pool incorporates many modern concepts including a zero entry, toddlers’ pool, several water spray features, a 3/4 meter diving board, four swimming lanes – 25 meters in length, a water slide, and a large perimeter deck area. Parking will be off-street on the east side of the building.
Funding
- This $3.22 million project is funded primarily by various grants.
- We have received 60+ Bonze Sponsors, 20 Silver Sponsors, 2 Gold Sponsors, 1 Platinum Sponsor and 1 Diamond Sponsor!
- All sponsors will be recognized on a sponsor wall at the new pool.
Naming Rights and Sponsorship
Click HERE for more ionformation on sponsoring this amazing project!